Buyers searching east of the city near Old Madras Road will come across Sattva Songbird, a community that Sattva Group has under construction on Budigere Road, Cheemasandra. It pairs high-rise apartments with a few row houses, and 6 May 2029 is its registered completion date. We set out the prices, unit mix, registration, surroundings and a booking checklist.
Price List and Extra Charges
Starting prices for each home are in the table further down, and the biggest 3 BHK plan costs Rs. 2.54 Crore. Saleable area is charged at roughly Rs. 14,000 a sq ft, rising to Rs. 14,600 for some types. Floor level changes the figure considerably in towers of some 30 floors.
An under-construction purchase brings further costs:
- GST charged on the value in the agreement
- Stamp duty (5% in Karnataka once the value exceeds Rs. 45 Lakhs, with cess and surcharge) and 2% registration
- View and floor-rise premiums
- The maintenance deposit, clubhouse charges and an extra car park if taken
Registration and stamp duty for the studio at Rs. 67.3 Lakh total around Rs. 5.1 Lakhs. Take Rs. 53.84 Lakhs borrowed at 8.5% and repaid in 20 years as an example: the monthly instalment is near Rs. 46,700. Other combinations of home and down payment are quick to test on the EMI calculator.
Unit Mix Across Four Towers
Songbird's opening phase spreads over some 12 acres, holding 58 row houses besides four towers of 1,321 apartments. The towers share two basements, and above the ground floor they have 29 to 31 levels, the highest touching 101 metres or so. Smaller homes fill the first two towers, with 471 apartments in one and 483 in the other at around 16 per floor. The third and fourth towers hold larger homes, 189 and 178 in number, at around six per floor.
The row houses, each a 4 BHK, are built as ground and two upper floors and separate from the apartment blocks. This table gives the registered count of each type, with apartment areas and starting prices.
| Home | Approx. carpet area | Saleable area | Count | Price from |
|---|---|---|---|---|
| Studio | 280 sq ft | 468 sq ft | 362 | Rs. 67.3 Lakhs |
| 1 BHK | 470 sq ft | 753 sq ft | 352 | Rs. 1.10 Crore |
| 2 BHK | 785 sq ft | 1,268 sq ft | 122 | Rs. 1.82 Crore |
| 2.5 BHK | 880 sq ft | 1,389 sq ft | 118 | Rs. 1.98 Crore |
| 3 BHK | 1,080 sq ft | 1,733 to 1,813 sq ft | 367 | Rs. 2.43 Crore |
| 4 BHK row house | 2,300 sq ft | On request | 58 | On request |
The carpet figure measures only what the home's walls enclose. Saleable area, the basis of the price, takes in balconies and part of the lifts, lobbies and clubhouses, so the carpet figure is just over 60% of it. Ask for both before comparing its rate elsewhere.
Buildings take up close to a quarter of the site; courts, gardens and roads fill the open remainder. Residents are to get four clubhouses with co-working space, a creche, a gym, a party terrace, multipurpose halls, a snooker room, badminton courts and indoor games. Of the 1,493 planned car spaces, 1,460 are covered.
Registration, Timeline and Water
Karnataka RERA lists the project as Sattva Songbird, registration PRM/KA/RERA/1251/446/PR/060924/007008. The grant, dated 6 September 2024, is to a Sattva Group company, Sattva Resi Private Limited. Plan approval by the Bangalore Development Authority is dated 15 July 2024.
The registered schedule opens on 1 June 2024 and closes on 6 May 2029. Reported progress rose from 18% (January 2026) to 21% (April) and then 24% (July 2026 update). Only that registered date binds the seller, whatever a sales team quotes.
The registration records that the land has no litigation. It names tankers and borewells for water, so buyers should ask how 1,300-plus homes will be supplied in summer. The neighbouring second phase, Sattva Songbird Phase 2, is registered on its own and finishes later.
Address and Daily Travel
The site is in Cheemasandra village (Survey Nos. 16/2, 16/1, 89), part of Bidarahalli Hobli, Bangalore East Taluk, with pincode 560049. It fronts Budigere Road, and the Budigere Cross junction with Old Madras Road (NH 75) is a few minutes' drive. Trips to the Outer Ring Road, Whitefield and KR Puram rely on these two roads.
Whitefield (Kadugodi), a Purple Line stop, is the nearest operating metro station and needs a road trip. Kempegowda International Airport is a 38 minute drive. The proposed Peripheral Ring Road would run close to Cheemasandra, though it has yet to move past planning. Test the existing roads with a drive to work at office hour.
Is It the Right Fit?
The choice is broad, running from studios through 3 BHK apartments beyond Rs. 2.4 Crore to row houses with four bedrooms. A studio or 1 BHK suits someone living alone, and equally an investor who would lease it to Whitefield office staff. The 2.5 BHK and the 3 BHK are for families comfortable with a 2029 handover.
A ready project serves better where a home is required within two years. So it does for those who favour a quiet, small building.
Who Is Building It
Bangalore-based Sattva Group has been in construction since 1993 and was earlier named Salarpuria Sattva. It develops malls, office parks, plotted layouts and apartments. Songbird's two phases share one group company as promoter.
Booking Checklist
For a large project with a long construction period, the checklist is:
- Match the flat number and tower to the registration shown by Karnataka RERA online
- Have the saleable, carpet and balcony areas of the exact home put on paper
- Count the lifts against roughly 16 homes per floor in the first two towers
- Compare a high floor with a mid floor on the floor-wise price sheet
- Ask which amenities and which clubhouse open along with the first handover
- Seek the plan for water supply, as borewells and tankers are the registered sources
- Pay into the RERA-registered project account and nowhere else