Should a Bangalore buyer book a flat mid-build, or pay for one that is complete? The answer turns on tax, the expense of waiting, the protection the law offers and what can be inspected beforehand. This guide takes each factor in turn, with the governing rule and a costed example.
Where in Its Life the Flat Is
A new flat can be bought at three broad points in a project's life:
- Pre-launch, when interest is invited before registration with Karnataka RERA
- Under construction, after registration, while work continues and payments run on a schedule
- Ready to move, after completion and the occupancy certificate, with handover on full payment
Pre-launch is where the law draws a line. Section 3 of the 2016 RERA Act stops a promoter advertising, taking bookings or selling until registration is in place. Treat a booking as secure only when its registration number can be looked up on the Karnataka RERA website.
Who Should Pick Which
Buyers who must shift soon, who are renting now and who have the down payment saved lean towards a finished flat. They know the full outlay on day one, and the EMI simply takes over from rent. People who would rather inspect a completed block than trust a plan prefer it too.
A flat still going up fits buyers who are building savings and can wait two or three years. They gain staged payments, a wider pick of units and a newer design, and they accept waiting costs and possible delay. Projects in their final stretch split the difference, as the wait is brief and much of the building is already standing.
How Payments Are Spread
Staged payment is the clearest advantage of buying during construction. The buyer's share and the loan are released milestone by milestone over two to three years. A finished flat, by contrast, asks for the down payment, duty and registration fee a few weeks after signing.
The law limits early demands as well. Under section 13, a developer may collect up to 10% of the cost before a registered written agreement for sale exists. Seventy per cent of buyer receipts must be kept in a separate account reserved for land and construction spending.
The Hidden Cost of Waiting
Two expenses run while a flat is being built. The first is rent: Rs. 30,000 each month for 30 months of construction totals Rs. 9 Lakhs.
The second is interest. Lenders release funds stage by stage, and the buyer services interest on every release while still living elsewhere. A finished flat starts the complete EMI immediately, but rent stops in the same month.
For scale, take a flat priced at Rs. 1 Crore, financed with 25% paid upfront as its loan cap requires. The Rs. 75 Lakhs loan at 8.5% for 20 years costs about Rs. 65,087 a month, an illustration only; the EMI calculator reworks it for other amounts and terms.
GST: When It Applies
Buying while construction is in progress brings GST, set at 5% of the overall price from 1 April 2019, and the developer cannot claim input tax credit. Affordable flats pay 1%, and in Bangalore that category means 60 sq m or less of carpet and a price of no more than Rs. 45 Lakhs.
The Central GST Act leaves a sale untaxed if full payment comes after first occupation or the completion certificate. That is why a developer flat bought once an occupancy certificate exists pays no GST, and neither does an owner's resale flat.
Payment dates, not building progress, decide the tax. Any instalment paid before completion on a flat booked mid-build remains taxable, even if the block is finished shortly after. Duty and registration are payable on either type when the deed is registered.
A Side-by-Side Sum
This illustration sets a Rs. 1 Crore flat under construction against a similar completed flat costing Rs. 1.05 Crore. Duty is taken at 5.6% after cess and surcharge, registration is 2%, and smaller items such as legal fees and deposits are excluded:
| Option | Price (Rs.) | GST at 5% (Rs.) | Stamp duty at 5.6% (Rs.) | Registration at 2% (Rs.) | All-in (Rs.) |
|---|---|---|---|---|---|
| Being built | 1,00,00,000 | 5,00,000 | 5,60,000 | 2,00,000 | 1,12,60,000 |
| Completed | 1,05,00,000 | Nil | 5,88,000 | 2,10,000 | 1,12,98,000 |
The 5% price advantage almost disappears after GST. Any real comparison should run on all-in totals rather than base prices.
Delay, Defects and Buyer Rights
For a flat still going up, delay is the main danger. Section 18 offers two routes when possession is late: withdraw and get the money back with interest, or remain and be paid interest per month of delay. Karnataka calculates that interest at State Bank's top MCLR plus 2%.
Those rights limit losses, yet enforcing them takes time. A developer's registered completion date and its delivery history on past projects are the better guides. A completed flat removes the risk, since the block is built and certified.
Both types carry a defect guarantee. Section 14(3) makes the promoter repair structural or workmanship defects, raised within five years from possession, inside 30 days and without charge. Section 19(10) gives buyers two months from the occupancy certificate to take over the flat, and handover comes only after that certificate.
Inspecting the Real Thing
Completed flats are bought after a walk-through of the exact unit. Daylight, the view, street noise, water pressure, lift delays, the allotted parking bay and how many neighbours have moved in can all be judged. A flat still going up is picked from layouts, a show flat and the site's state on that day.
What a buyer gives up with a finished project is choice. Booking at launch opens up every floor, orientation and plan, while late buyers take what is left. Unsold flats in a completed block may have aged a few years, so check the condition of lifts, pumps and painted surfaces.
Paperwork to Ask For
Ahead of paying for a flat under construction, look at:
- The project's registration number, promoter and committed completion date, verified through Karnataka RERA online
- Its quarterly construction updates
- A schedule linked to building stages, with GST quoted on a separate line
- The developer's handover history on past city projects
Ahead of paying for a finished flat, look at:
- The occupancy certificate issued for that block
- An encumbrance certificate, khata papers and the newest property tax receipt
- Electricity and water connections held by the building, and the maintenance charged each month
- A written term making the entire price payable once the occupancy certificate is out, so the sale stays GST-free