Book A Home

Bengaluru Business Corridor: A Property Buyer's Guide to Package 1 and the Route

By Book A Home Editorial Team·9 October 2026·6 min read
Bengaluru Business Corridor: A Property Buyer's Guide to Package 1 and the Route

If you are shopping for a plot or home in the north or east of Bangalore, you have probably heard that a big ring road is coming. What changed in June 2026 is that a contractor was named for its first part. The notes below take the questions buyers ask in turn: what the road is, what has been awarded, who gets paid for land, and what to check before putting money near it.

Why Does the Road Exist?

The aim is to let lorries and through vehicles skip the city. That job was once given to the Outer Ring Road, which is today an urban road with offices and housing on both sides. The new project, called the Bengaluru Business Corridor and earlier the Peripheral Ring Road, is meant to do it again further out.

The agency behind it is the Bangalore Development Authority, and the basics are these:

  • A length of about 74 km, with entry and exit only at interchanges
  • A start on Tumakuru Road to the north-west and an end on Hosur Road to the south-east
  • Crossings of Old Madras Road, Ballari Road and Sarjapur Road along the way
  • With the NICE Road on the west, a loop of nearly 117 km
  • Eight main lanes and service roads on each side
  • A strip reserved for a possible metro line
  • A width of 65 metres, down from the 100 metres notified at first (changed in October 2025)

The project is split into three packages and costs an estimated Rs. 27,000 crore, where land is the largest item. Only Package 1 has a contractor so far.

What Has Actually Been Awarded?

Package 1 is the roughly 20 km between Madavara, which adjoins the exhibition grounds off Tumkur Road, and Ballari Road. In March 2026 global bids were called, against an estimate of Rs. 3,348 crore. Two companies bid on 8 May 2026, and by June the letter of acceptance had gone to Shankaranarayana Constructions of Bangalore.

Completion is due within 36 months of the work order. Three cloverleaf interchanges, two railway bridges and 7.5 km or so of elevated road are part of the job, and some 83% of the required land is said to be in hand.

Acceptance letters only name the winner, and signing, handing over land and bringing machinery to site are still to come. Even so, the tenders of 2022 and 2024 were both cancelled, so no earlier attempt got this far.

Who Gets Paid, and How?

Close to 2,600 acres belonging to private owners are involved, and compensation has been fought over for a long time. The state now lets them pick from five options rather than taking cash alone:

  1. Cash at the assessed value
  2. Transferable development rights (TDR) to use or sell
  3. Additional floor area ratio on the remaining land
  4. A developed residential site in a layout
  5. Land for commercial use next to the road

Cash is certain but capped. TDR and added floor area ratio both rely on buyers existing for them, and a developed site relies on a finished layout. A landowner who receives a notification ought to consult legal and valuation help first.

Land for the remaining packages is still being acquired. Because Package 1 connects two highways, it can serve traffic on its own, and the eastern and southern stretches will move at their own speed.

Which Areas Benefit First?

The awarded stretch crosses villages past Yelahanka, near Hesaraghatta Road, just outside the present city limit, where plotted layouts and apartments keep appearing. Residents there stand to gain quicker links to both highways and the airport road.

Later packages should cross Old Madras Road, Whitefield and Sarjapur and end by Electronic City on Hosur Road. Among the city's zones, North Bangalore is where the award applies today.

Is Land Near the Road Worth a Premium?

Possibly, though the risk of the road never being built has fallen only partly. Sellers have been using the corridor as a selling point since long before any contract, and a price asked today often assumes a road that needs three years at the least.

Between interchanges the road allows no access at all. A plot beside it with no junction close by gets noise and nothing else, so the best-placed land is beside a junction with a good feeder road.

Judge the property as if there were no corridor. If its existing roads, schools and workplaces justify the price, the road is an extra. If the corridor is the sole reason, the buyer takes all the delay risk.

Buyer's Checklist

These steps suit plots, villas and flats in villages close to the route:

  1. Look up the survey number on the notified alignment and see where it falls relative to the 65-metre corridor
  2. Find out if the land was caught by the earlier 100-metre notification, and if that was withdrawn
  3. Find the interchange planned closest to the land and the road that serves it
  4. Establish which package covers the stretch, and how much acquisition is complete
  5. Verify the layout sanction, land use conversion, khata and encumbrance record
  6. Search for a RERA registration on the Karnataka portal when buying an apartment or a plotted project
  7. Set the asking price beside similar land farther from the road

A contract on the first stretch shows the project is moving, but the road will open section by section across several years. Paying today's value for land with clean records lets a buyer benefit without depending on the road.

Frequently Asked Questions

What does the name Bengaluru Business Corridor refer to?+
The Peripheral Ring Road under a new name, planned by the Bangalore Development Authority as a limited-access road about 74 km long. It runs across the northern and eastern sides of the city between Tumakuru Road and Hosur Road.
Is any stretch of the road under contract?+
The first package is. A letter of acceptance went to Shankaranarayana Constructions in June 2026 for roughly 20 km from Madavara, on Tumakuru Road, to Ballari Road, and the contract period is 36 months.
How much will Package 1 cost?+
The tendered estimate was Rs. 3,348 crore. Across the whole corridor the figure is about Rs. 27,000 crore, and land is the bulk of that.
What do land owners receive for their land?+
A choice among cash, transferable development rights, additional floor area ratio, developed residential sites and commercial land beside the road. The risks differ, so it helps to take legal and valuation advice.
Does land near the corridor deserve a premium?+
Only if the location is good on its present roads and services. At least three years are needed to build the road, and access is only at interchanges. Check the survey number against the notified alignment before paying.

Related Reads